Project Controls

Alüm CAST BUILD A.O Budget

Budget details export organized into CAST Build cost controls: revised budget, commitments, job-to-date, forecast/EAC, owner invoicing, and over/under exposure.

Status Report Open Budget Exceptions / Needs Review Open Budget Modification Platform Open Commitments Accounting Tie-Out Editable Budget Workspace Dynamic Forecast View Budget Audit

Revised Budget

—

Estimated at Completion

—
EAC / forecast

Projected Over / Under

—
positive is savings; negative is overrun

Owner Invoiced

—
cost to date billed to owner

Committed Costs

—
commitments in CAST BUILD A.O export

Job to Date

—
posted/recognized cost

Monthly Cost Curve

Budget vs actual by month
All Costs · MonthlyBudget / EACActual / JTD

Category Mix

CategoryBudgetJTDO/U

Read-first planning curve. Monthly allocation is modeled from cost-code category and project schedule phase, then reconciled to current CAST BUILD A.O revised budget and job-to-date cost totals.

Budget by Division

DivisionRevisedEACOver/Under

Top Budget Risk Rows

Budget CodeCost CodeRevisedEACOver/Under

Budget Input + Audit

Loading audit…
Input baseline

—

Audit posture

—

Revision reconciliation

—

CheckStatusDelta / Detail

Editable Budget Workspace

No local edits yet.
Planning layer: edit proposed revised budget, EAC override, cost mapping bucket, and notes locally. This is for scenario planning only; it does not update CAST BUILD A.O, Dropbox, GitHub, or accounting exports.
Scenario Revised Budget

—

baseline plus local budget deltas

Scenario EAC

—

override EAC where entered, otherwise CAST BUILD A.O EAC

Scenario Over / Under

—

scenario revised less scenario EAC

Budget CodeCost MappingBaseline RevisedBudget DeltaScenario RevisedBaseline EACEAC OverrideScenario O/UNotes

All CAST BUILD A.O Budget Rows

Budget CodeCost CodeTypeRevisedCommittedJTDEACO/U